Building the Climbing kiln

Building the five-chambered climbing kiln

We have eight wood-fired kilns in seven types at our kiln site.
The maximum limit to use refractory bricks is usually about 150 times.
We often fire the kilns so when the 150 limit is reached we build a new kiln. This happens between 7 to 8 years.
The followings is a report when we built a five-chambered climbing kiln in March, 2012
Next time we build a new kiln in the future, we will make regenerator to effectively utilize exhaust heat to produce electric power or other kinds of energy.

Conditions of building a five-chambered climbing kiln
All of staff worked for building the kiln according to a design drawing by Senior Managing Director, Kudo.

310DSC_0596_thumb_4

310DSC_0609
310DSC_0608

 

▼Go to the last report.

February 21 (Tue)

P1050455P1050459P1050467
This was the old climbing kiln which kept working for 10 years.


February 22 (Wed)

222P1050521222P1050522222P1050525
For preparing to break down the old kiln, we removed dirt which covered the kiln.


Feb 23 (Thur)

223P1050529223P1050538
All of the studio staff went through a purification ceremony. The old climbing kiln was broken down in one go with the heavy machinery.
This “doing something in one go” is “Tsugaru Kanayama way.
223P1050543223P1050547
The old kiln was broken down in half-day. The roof had a gaping hole in it. Chimney used to be installed in the hole. (upper right side of the above picture).


Feb 24(Fri)

We started basement planning in the morning.
224P1050551224P1050555
Excavation started from the afternoon.
A master Potter, Ryoji, handled power shovel.
224P1050561224P1050566
Fundamental kiln construction which was placing of concrete to the firebox started. Making firm foundation is important for building the kiln.
We use concrete for foundation of the kiln.


Feb 25 (Sat)

225P1050589225P1050594
Risako the board chairperson,together with the female staff and male staff worked for concreting the foundation.
225P1050596225P1050603
We worked for fundamental construction of the first and the second chambers this day.


Feb 26 (Sun)

226P1050613226P1050628

226P1050632226P1050636
Bricklaying of the firebox started.


Feb 27 (Mon)

227P1050641227P1050642
Work for building the kiln seemed to be going well this day.
227P1050644227P1050649
However, a part of kiln-equipped pottery workshop was collapsed under the weight of snow!
In spite of having such an accident, work of building the kiln was going well.


Feb 28 (Tue)

228412282
We reused bricks which removed from the old kiln after cleaning those well. Bricks for the firebox were already laid up this much as seen in the picture.
22812283
We reused bricks which removed from the old kiln after cleaning well.


March 1 (Thur)

313314
The last concreting work
322
Bricklaying work was going well.
The walls of the first chamber being built just a little .


March 3 (Sat)

331332
The walls of the first and second chambers were being built gradually.
Constructing kiln floor team started working simultaneously with the wall team. The kiln floor team were progressing ahead.
333334
The kiln was getting close to the shape in accordance with the design.
335336

337338

33913310
This is our fashion to bear the cold and dust.


March 4 (Sun)

343344
The walls being built were getting higher.

341342
Construction of the first, the second, and the third chambers’ walls of the kiln were completed!


March 5 (Mon)

120305_1734120305_1733
Kiln construction was going on even after getting dark.
Building the kiln was important work, so staff was receiving detailed directions.
120305_1733120305_1732
The arch of the firebox under construction was like this shape as seen in the picture at this point.
Thickness of the wall was about 50 cm (about 19.6inches).src="http://kanayamayaki.sakura.ne.jp/wp-content/uploads/2015/07/0305005.jpg" alt="120305_1731" width="292" height="175" />120305_1731


March 6 (Tue)

361362
Building the arch on top of the kiln was steadily making progress.
The picture of the above right side was the view of the kiln from the backside.
363364
The picture of above left side was the view of the arch from the entrance.

The roof was being built one after another, and the kiln was close to completed shape.


March 7 (Wed)

371
Building the roof of the third chamber was finished.
Bricklaying on the fourth chamber was finished, so building the kiln work was getting near completion.
372
Memorial bricks which our customers wrote messages on those were piled up.
We are going to use this kiln having these messages with taking good care.
To our customers who wrote messages on these bricks:
We will be happy to welcome you anytime, so please visit us anytime to see the kiln.
373
This was an empty room between the last chamber and chimney in the kiln.
Inside the kiln was getting complicated as seen in the picture.
This was the first attempt that built the empty room between the last chamber and chimney in the kiln, so we were looking forward to using the kiln after built to see how it works.
374
Bricklaying was piled up until about the 160cm (about 63inches) high.
Building the kiln would be the final stage next day.
The roof of all the chambers seemed to be finished building next day at this point.
Work of building the kiln was progressing with the fast and good pace.

 


March 8 (Thur)

All of members engaged in building the kiln were working together this day, so that building the kiln work was making good progress.
381382383384385386
The chimney being built was getting much higher as seen in the picture.
387388
Cleaning bricks taken from the old and broken-down kiln was almost finished.


March 9 (Fri)

39113921

393
The following works were Tsugaru Kanayama Pottery way:
Digging a hole in the ground and agitating excavated ground with the heavy machinery.
Preparing dirt to cover the kiln.
3941
Many staff were getting on the top of the kiln and already making ready to pile up dirt on the kiln to cover the kiln..
The bricks on the roof were double-layered. Moreover, we cover the kiln by dirt for moisture retention.

 

396396-1397398
Dirt was daubed to the upper of the kiln.
The roof was being built sturdily, so the kiln was impregnable even some staff were getting on the roof together as seen in this picture.
3993910

39P1050660
Dirt was daubed on the top of the kiln, and building the kiln was almost completed.
39P1050655
39P1050659
39P1050664

 

39P1050662
39P1050653


Steps were made to make working around the kiln be easier.
Building the kiln would be completed after added the finishing touch next day.


March 10 (Sat)

310DSC_0621310DSC_0623
We added the finishing touch to the kiln this day. Removed excess mortar from the inside the kiln, and a joint filling was performed.

310DSC_0613310DSC_0615
The finishing work was being done very carefully.
310DSC_0617310DSC_0631

310DSC_0619310DSC_0627
Some staff placed concrete as final for forklift work.

310aDSC_0639_thumb_1
Staff who built the kiln (and five more besides above members)

310DSC_0558_thumb_1310DSC_0591_thumb
The kiln viewed from the side which had the hole to put charcoal inside the kiln.
310DSC_0588_thumb310DSC_0576_thumb
The kiln viewed from the kiln entrance side.
310DSC_0633
Building a chimney was completed.
The height of the chimney was seven meters (about 275 inches).


March 11 ( Sun)

311DSC_0645311DSC_0651
We had a consecration ceremony for the new kiln this day.
311DSC_0652311DSC_0660
Sacred atmosphere which was different from during working was created at the kiln site once the ceremony started.
311DSC_0684311DSC_0689
The first firing at the new kiln was performed as a part of the ceremony.
Master Potter, Ryoji, and all of staff prayed for the new kiln.


Specifications of the five-chambers climbing kiln

Chamber rooms five
Kiln capacity 107ft2
Numbers of used bricks About 20,00
Length 42ft

▲top